|
Ground Water Recharge
The groundwater recharge was computed
separately for monsoon and non-monsoon season as given in the methodology.
While calculating the monsoon recharge the normalisation was done as per the
guidelines. The infiltration rates were taken as per the recommended norms and
wherever corrections needed, were done considering the field conditions and data
availability. Since the computation was done block wise, the details of the
normalization/modification etc were also carried out block wise for greater
accuracy. The district wise figures of monsoon and non-monsoon recharge are
given in Appendix 1 and in Appendices 2 to 15.
The recharge computed using the 1997
methodology is found to be less by 1059.48 MCM when compared to that of the 1984
methodology. Table 4.1. gives a comparison of the same.
Table
4.1 Comparison of the recharge figures of 1992 (1984
methodology) and 1999 (1997 methodology)
|
Sl.No. |
District |
Recharge in MCM |
Deviation MCM |
% |
|
|
|
1992(1984 methodology) |
1999(1997 methodology) |
|
|
|
1 |
Trivandrum |
299.57 |
308.51 |
+8.94 |
+2.98 |
|
2 |
Quilon |
464.95 |
495.61 |
+30.66 |
+6.59 |
|
3 |
Pathanamthitta |
474.93 |
347.00 |
-26.92 |
-7.19 |
|
4 |
Alleppey |
572.00 |
466.08 |
-105.92 |
-18.51 |
|
5 |
Kottayam |
473.98 |
521.06 |
+47.08 |
+9.93 |
|
6 |
Idukki |
458.03 |
269.04 |
-188.99 |
-41.26 |
|
7 |
Ernakulam |
750.65 |
618.43 |
-132.22 |
-17.61 |
|
8 |
Trichur |
835.24 |
774.99 |
-60.25 |
-7.21 |
|
9 |
Palghat |
885.59 |
823.92 |
-61.67 |
-6.96 |
|
10 |
Malappuram |
685.56 |
557.29 |
-128.27 |
-18.71 |
|
11 |
Calicut |
520.09 |
366.41 |
-153.68 |
-29.55 |
|
12 |
Wayanad |
424.55 |
324.39 |
-100.16 |
-23.59 |
|
13 |
Cannanore |
733.09 |
591.89 |
-141.2 |
-19.27 |
|
14 |
Kasaragod |
423.06 |
376.18 |
-46.88 |
-11.08 |
|
|
Total |
7900.28 |
6840.80 |
-1059.48 |
-13.41 |
The
maximum deviation is shown by Idukki (-41.26%) followed by Calicut
(-29.55%) and Wayanad (-23.59%) districts. This is mainly due to the
omission of the hilly area where the slope is more than 20%. All other
districts have deviation of less than 20%. The less recharge by other
districts is mainly attributed to the non-inclusion of potential
recharge in the 1997 methodology.
Thus
it can be seen that the recharge from rainfall is 5693.6 MCM (both
monsoon and non-monsoon seasons) and that of canal and irrigation fields
are 1147.20 MCM. The total recharge thus came to 6840.80 MCM.
The
district wise recharge figures are given in Appendix-1 and block wise
monsoon and non-monsoon recharge figures are given in Appendices from 2
to 15.
Net Ground Water Availability
The
net groundwater availability was calculated as per the norms recommended
in the 1997 methodology. From the block wise figures of recharge 10%
was deducted as unaccounted losses and natural discharge if the recharge
was computed based on rainfall infiltration method and 5% if the
recharge was computed based on water level fluctuation method. From the
block wise figures the district wise figures were computed. The
district wise figures are given in Appendix 1 and the block wise figures
are given in the Appendices from 2 to 15. The net ground water
availability of the State is 6229.04 MCM.
Ground Water Draft
The
existing domestic and Industrial groundwater draft were computed as per
the methodology and the district wise figures are given in Appendix I
and block wise figures in Appendices from 2 to 15. The existing
districtwise gross ground water draft for irrigation is given in
Appendix I and table 1 and block wise figures in Appendices from 2 to
15. In the earlier methodology, the domestic draft was computed
separately and deducted from the total recharge to arrive at utilizable
recharge. In the present methodology the domestic draft is also taken
along with the other drafts.
The
gross ground water draft for all the uses is computed as 2693.38 MCM for
the State. The domestic and the industrial drafts account for 40.73% of
the total draft (1097.36 MCM), the irrigation draft accounts for 59.27%
of the total draft (1596.02 MCM). These figures are given in Appendix
1.
The
block wise figure computed under various category of draft along with
the total gross draft is given in Appendices from 2 to 15.
Net Ground Water Availability
for Future Irrigation Development
The
balance ground water available for future irrigation was computed after
deducting the gross draft for irrigation and allocation for domestic and
industrial water supply for next 25 years from the net annual ground
water availability. A balance of 3221.23 MCM is available for future
irrigation development as per the new methodology. The district wise
figures are given in appendix 1 and the block wise figures are given in
Appendices from 2 to 15.
Stage
of Development
The
stage of development was computed for each block separately and it
indicates that 7 numbers of block show development of more than 100%, 6
show development between 90 and 100%, 6 between 80 and 90% and 12
between 70 and 80%. The district wise stage of development is given in
Appendix 1 and the block wise figures are given in Appendices from 2
to15.
Categorisation of Blocks
The
categorisation of 151 blocks based on development and the long term
trend in water level is given in the Appendix-16. The long term water
level trends of pre- and post-monsoon were taken to categorise the
blocks. Following is the list of over-exploited, critical and
semi-critical blocks of the State (Table 4.6.1). The remaining 136
blocks are falling under safe category.
Table 4.6.1 Details of over-exploited, critical and semi-critical
blocks
Over exploited (3 Nos)
-
Chirayinkil : Trivandrum district
-
Kasaragod : Kasaragod district
-
Kodungallur : Trichur district
Critical (6 Nos)
-
Tallicherry : Cannanore district
-
Parassala : Trivandrum district
-
Athiyannur : Trivandrum district
-
Mukhathala : Kollam district
-
Anchalumoodu
: Kollam district
-
Balusseri : Calicut district
Semi- critical (6 Nos)
-
Pampakuda : Ernakulam district
-
Paraur : Ernakulam district
-
Mulanthuruthi : Ernakulam district
-
Mala : Trichur district
-
Calicut : Calicut district
-
Nemom : Trivandrum district
Domestic and industrial needs for 2025
The
figures were computed for each block. The total projected demand for
domestic and industrial needs worked out as 1411.79 MCM. The district
wise data is presented Appendix 1. The blockwise figures are given in
Appendices from 2 to15.
Potential recharge
The
potential recharge was computed for all the blocks underlain by coastal
alluvium where the pre-monsoon water level is less than 5.0 m bgl. The
potential recharge computed is 1989.47 MCM. The details of district
wise figures are given in are given in Appendix-17 and the block wise
figures for each district are given in Appendices from 17.1 to 17.14.
These figures are not considered for computation of gross recharge.
This can also be considered for computation in order to give a realistic
figure of the stage of development of certain blocks, especially over-
exploited and critical blocks.
Static ground water resources
The
static ground water resource is computed considering the fluctuation as
20 m. In the hard rock it is assumed that the potential fractures exist
upto 100 mbgl. In the sedimentary basin, the actual thickness of
potential zones were computed and average figures were worked out. This
was done block wise. The brackish water potential also was computed
separately for sedimentary areas. The fresh water static resource is
5576.55 MCM and the brackish water resource is 679.00 MCM. The details
of district wise figures are given in Appendix-18 and the block wise
figures for each district are given in Appendices 18.1 to 18.14.
|